Williams awarded Ranger Pipelines $3.6 million to replace 8,300 feet of sewer mains and laterals; state funding requires completion by Sept. 1, 2029.

Share

Topics

COLUSA, Calif., Oct. 3 (Colusa Online) — Williams, California, is moving ahead with a $3.6 million construction contract to replace about 8,300 feet of deficient sewer mains and laterals in several street and alley corridors. The work will also rehabilitate five deficient manholes, Colusa County News reported.

For residents in the project area, the work concerns the wastewater system, not a funded replacement of drinking-water lines. State funding will cover the sewer project, and city officials say the funding agreement requires the improvements to be completed by Sept. 1, 2029.

What work did the council approve?

The Williams City Council awarded Ranger Pipelines a $3,608,377 construction contract on Sept. 16, 2026, after seven companies competed for the work, Colusa County News reported. Ranger’s base bid was $3,567,877. The council added $40,500 to rehabilitate the five manholes.

Sewer mains are the larger pipes that collect wastewater, while laterals connect properties to the sewer system. Manholes provide access to underground sewer lines. The contract covers replacement of deficient pipes as well as rehabilitation of those access points.

Where will the work take place?

The base work extends from B Street at the railroad crossing to D and 11th streets, according to Colusa County News. Another section runs from the alley along D Street between Sixth and Seventh streets to I Street and the alley between Eighth Street and Redinger Way.

Residents in these corridors are the population affected by the described sewer work. The project’s approximately 8,300 feet of pipe replacement includes both mains and laterals, rather than mains alone.

How will Williams pay for it?

The State Water Resources Control Board awarded Williams $5.46 million through the Clean Water State Revolving Fund for the sewer project. City officials said no city money is required to complete the project, including its construction contingency.

A contingency is money reserved for unexpected construction costs. Officials said approximately $1.85 million remains after the contract award to cover construction administration and unexpected expenses. Construction administration is the management and oversight needed to carry out the contract; that remaining balance is not all reserved for additional pipe work.

Colusa County News reported that the available balance leaves slightly less than a 20% contingency. Additional sewer sections could be added if construction does not use the full contingency.

Will drinking-water lines be replaced too?

The wastewater grant cannot pay for drinking-water improvements, and sewer and water lines must be placed in separate trenches, Colusa County News reported.

Coordinating sewer and drinking-water work would likely reduce contract administration and mobilization expenses, the outlet reported. Mobilization means bringing crews, equipment and other resources to a work site. The potential savings concern coordinating the work, not using wastewater funding to pay for drinking-water improvements.

Community Development Block Grant funding could allow both systems to be improved during a future project, according to Colusa County News. Williams is also completing an income survey that could make the city eligible for additional water and wastewater grants if it qualifies as a disadvantaged community, the outlet reported.

Share

Topics

Sandra Schumer

Raised in Rohnert Park, California, Sandra Schumer is the Woodland reporter for Times Media Service. Schumer covers local news in Woodland, including city government, schools, agriculture, public safety, development and community life, along with California elections and crime and justice. Schumer holds a master's degree in mass communications.